Construction of Nicaragua canal to begin Dec. 22 -committee

by Reuters
Friday, 21 November 2014 01:58 GMT

A fisherman casts a fishing net at Lake Nicaragua, September 19, 2014. REUTERS/Oswaldo Rivas

Image Caption and Rights Information

Opponents concerned about canal's effect on Lake Nicaragua, an important fresh water source for the country, and impact on poorer communities

MANAGUA, Nov 20 (Reuters) - Construction of Nicaragua's $50 billion Interoceanic Grand Canal, expected to rival the Panama Canal, will begin Dec. 22 after feasibility studies have been approved, the committee overseeing the project said on Thursday.

The route suggested for the 172-mile (278-km) canal, which would be longer, deeper and wider than the Panama Canal, was approved in July. Construction will be led by Hong Kong-based HK Nicaragua Canal Development Investment Co Ltd (HKND Group).

Opponents of the plan are concerned about the canal's effect on Lake Nicaragua, an important fresh water source for the country, as well as the impact on poorer communities.

Committee member Telemaco Talavera said the feasibility studies were expected to be approved next month. The plan is to finish the canal within five years, with it becoming operational around 2020.

Officials said some small adjustments were being made to the overall project, including dredging stretches of a lake rather than using underwater explosives.

Bill Wild, HKND Group's chief project adviser, said more than 1 million cubic meters of earth will be dug up in the first year of work.

"This is a massive project, nobody can imagine how large and challenging a project it is, and it will possibly end up being the largest movement of earth that has ever been undertaken in the world, so it will be a massive challenge," said Wild.

He added that the work beginning in December will include building access routes to the project, installations for 50,000 workers and the construction of a temporary port on the Pacific coast.

The proposed canal would pass through Lake Nicaragua, Central America's largest lake, and will be between 230 meters and 520 meters (755 feet to 1,706 feet) wide and 27.6 meters (90 feet) deep, HKND has said.

Chinese businessman Wang Jing is behind the canal plan, though he has no prior experience developing or financing big infrastructure projects like the planned canal.

Wang only established Hong Kong Nicaragua Canal Development Investment Co (HKND) in August 2012, prompting some to question whether the project was viable.

(Reporting by Ivan Castro; Writing by Christine Murray and Simon Gardner; Editing by Alan Crosby)

Our Standards: The Thomson Reuters Trust Principles.

-->